Project Phase 1

Military Road STAGE 1: Duration 200 Days (October, 15th 2014 to May 27th, 2015): All Lanes Remain Open during rush hours. Lanes will be shifted towards the shoulders to create Median Workzone along Military Road between Oregon Ave NW & Joyce Road intersections.

Project Phase 2

Military Road STAGE 2: Duration 262 Days (November, 5th 2014 to August 25th, 2015): All Lanes Remain Open during rush hours: Lanes will be shifted towards the shoulders to create Median Workzone along Military Road between Joyce Road & 14th Street NW intersections.

Project Phase 3

16th Street NW STAGE 1 Southbound Lane Closures: Duration 55 Days (March 27th, 2015 to May 31st, 2015): One Lane in each direction will be maintained on the 16th Street NW One Lane in each direction on the Military Road NW under the Bridge will be maintained During four (4) Weekends in this phase to demolish […]

Project Phase 4

16th Street NW STAGE2 Northbound Lane Closures Duration 55 Days (May 22nd, 2015 to July 15th, 2015): One Lane in each direction will be maintained on the 16th Street NW One Lane in each direction on the Military Road NW under the Bridge will be maintained During four (4) Weekends in this phase to demolish […]