16th Street NW STAGE 1 Southbound Lane Closures: Duration 55 Days(Mrch 27th, 2015 to May 31st, 2015):
- One Lane in each direction will be maintained on the 16th Street NW
- One Lane in each direction on the Military Road NW under the Bridge will be maintained
- During four (4) Weekends in this phase to demolish and rebuild the bridge:
- the 16th Street Bridge will be closed to all traffic for a continuous period of time for 8 hours
- Military Road will be closed under the bridge to all traffic for a continuous period of 32 hours
- The Closings will occur on weekends between 9:00PM on Friday and will reopen before 5:00 AM Monday morning.
- During the bridge closures, traffic will be detoured onto Kalmia Road, Military Road and 14th Street. Motorists will be notified in advance to avoid the 16th Street Bridge.